Sidewalk - Bentley Street
20200011
Project Details
  1. Project Name
    Sidewalk - Bentley Street
  2. Description
    New sidewalk along both sides of Bentley to provide connectivity in a high pedestrian area, allowing residents safe access to Scarborough Elementary and James Driver Park.
  3. Location
    East Aldine
  4. Type of Project
    Sidewalk & Trail
  5. Estimated Cost
    $350,000
  6. Construction Start
    1st Qtr, 2021
  7. Construction Completion
    2nd Qtr, 2021
  8. Current Status
    Substantially Complete
Project Team
  1. Contact Number
    (713) 274-2222
  2. Media Contact
    comms2@pct2.hctx.net
  3. Contact Form
  4. Department
    Engineering & Capital Improvement Projects Department